A proposed $1 billion data centre backed by 44 diesel generators in Artarmon’s industrial precinct is facing scrutiny over overnight noise, heavy vehicle movements and strain on local infrastructure.
Gateway Capital plans to build the five-storey facility at 12 Frederick Street, just metres from Royal North Shore Hospital. According to preliminary planning documents, the nearest homes sit roughly 230 metres to the east, across the North Shore railway line.
The development, to be built and operated in partnership with Lendlease, would replace existing warehouse, office and indoor recreation spaces with 11 server halls running 24 hours a day. A medical centre borders the site immediately to the south, with the broader hospital campus farther along Reserve Road. The proposal is currently at the environmental impact statement (EIS) stage.

Overnight Cooling Noise and Generator Testing
State planning officials have directed the developer to model operational noise from rooftop cooling equipment, with a sharp focus on overnight hours. The acoustic study must examine low-frequency noise, map predicted sound levels and determine whether hum from the plant could disrupt nearby residents’ sleep. Crucially, it must also factor in cumulative noise from surrounding developments, including rival data centres.
Meanwhile, the NSW Environment Protection Authority (EPA) has demanded clarity on the facility’s 44 backup diesel generators. Gateway must detail how often the units will be tested, the duration of each test and how many could run simultaneously, alongside modelling for noise and diesel emissions during both routine maintenance and emergencies.
The precinct is rapidly becoming a data hub. NEXTDC already operates two centres on nearby Broadcast Way, while Goodman is constructing another at Lanceley Place—a project that recently drew objections from Greenwich residents over noise, truck traffic and road wear.
Traffic Pinch Points and Driveway Access
While Willoughby City Council officers raised no in-principle objection during initial consultations, they flagged the congested intersection of Frederick Street and Reserve Road—a critical arterial link to the hospital—as a key concern. Officers noted that early concept plans appear to retain the Frederick Street driveway while removing two existing access points on Reserve Road, and have asked Gateway to formally confirm those changes.
Under state assessment requirements, the developer must map proposed haulage routes and estimate demolition and construction truck volumes. The traffic modelling must assess nearby intersections and account for overlapping construction from neighbouring projects.
Council has also instructed Gateway to prove that trucks waiting to load or unload can be accommodated entirely on site, rather than queuing on surrounding streets.
Cooling Choice Will Shape Water Demand
Running 11 server halls around the clock carries a hefty utility footprint. The facility will require an estimated electrical load of 81 megawatts, supported by two on-site substations. NSW Planning has requested forecasts for daily, peak and annual power consumption, while Ausgrid has asked Gateway to assess local network capacity and identify necessary grid upgrades.
Water use remains an open question. Preliminary designs feature rooftop chillers and dry coolers, though Gateway is still finalising its cooling technology. Sydney Water has requested detailed projections for drinking-water demand, options for alternative water sources and strategies to curb consumption.
Council Seeks a Tally of Jobs Gained and Lost
Council is also pressing the developer to substantiate its employment claims. Gateway’s August lodgement estimated the project would generate 250 construction jobs and 50 ongoing operational roles. Council officers have asked for a transparent breakdown of how those figures were calculated, including a clear tally of how many existing jobs will be retained or displaced. When Gateway and its investment partner agreed to acquire the site in 2023, it housed 13 separate warehouse and office tenancies.
The state government has yet to set a date for the EIS to go on public exhibition. Once released, residents will be able to review the full assessments and lodge formal submissions. Community members can register for project updates via the NSW Planning Portal under reference number SSD-139545990.